📍 37.5146776, -77.3671403 📐 15.99 acres 🏷️ APN: 811-712-4375 🔌 2b8a1783-f6da-4d1e-bae4-9ed490f4fa58 📅 Generated May 12, 2026 12:49 PM 🆔 VA002392
Go
BESS Score: /10 Buildable: ac Nearest Sub: CHARLES CITY ROAD (0.1 mi) Zoning: Vacant Land - Commercial-Vacant Land
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

BERGESON JAMES FREDERIC TRUSTEE
15.99
811-712-4375
Vacant Land - Commercial-Vacant Land (MIXE)
Battery Energy Storage
Henrico
51087
01720A0000 0003; WILLIAMSBURG ROAD AC 15.74 10 A2 14

⚡ Infrastructure

2b8a1783-f6da-4d1e-bae4-9ed490f4fa58
CHARLES CITY ROAD
0.1 mi
230 kV
230kV at 0.0 mi (VIRGINIA ELECTRIC & POWER CO)
Public
POI Onsite
Great

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Loading from layers...

📊 Assessment

Go
/10

🤖 AI Site Assessment — Gemini Deep Research

Site Diligence Analysis: CHARLES CITY RD, Henrico, VA

As a senior BESS site evaluation analyst for Sunland America Corp, I have performed a comprehensive diligence analysis for the property located at CHARLES CITY RD, Henrico, VA (APN: 811-712-4375). This analysis focuses on the property's suitability for a distribution-scale (≤5MW) or utility-scale Battery Energy Storage System (BESS) project, considering all critical development factors.

1. Site Access & Topography

  • Road Access Quality & Equipment Delivery: The property benefits from "Public" road access via CHARLES CITY RD. This is a significant advantage, ensuring straightforward access for construction and operational vehicles. CHARLES CITY RD is a well-established arterial road in Henrico County, suggesting good quality and capacity for heavy equipment. The "POI Onsite" designation further indicates direct access to the point of interconnection, minimizing the need for extensive off-site infrastructure development.
  • Terrain Characteristics: The land use is described as "Vacant Land - Commercial-Vacant Land" with a "Buildability: Great" rating. This strongly suggests a relatively flat or gently sloping topography, ideal for BESS development which requires a stable, level pad for battery containers, inverters, and transformers. Henrico County generally features mild terrain, further supporting this assessment. Minimal grading and site preparation costs are anticipated.
  • Heavy Equipment Access: Given the public road access and "Great" buildability, heavy equipment such as large transformers, battery containers, and cranes should have unhindered access to the site. No significant topographical barriers or narrow access points are indicated.
  • Access Easement Concerns: While public road access is confirmed, specific access easements for the BESS project itself (e.g., for utility lines, internal site roads) are not detailed. This will require verification during the survey phase to ensure clear ingress/egress and utility routing rights. No immediate red flags are apparent.

2. Environmental Constraints

  • FEMA Flood Zone Designation: The FEMA Flood Zone is currently Unknown. This is a critical data gap. A detailed flood zone determination is paramount. If the site falls within a 100-year floodplain (AE or VE zones), significant design modifications (e.g., elevated platforms, floodproofing) and more stringent permitting will be required, substantially increasing costs and project timelines. This could be a project killer if mitigation is infeasible.
  • Wetlands Presence & Setback Requirements: Wetlands presence is also Unknown. This is another critical environmental unknown. Wetlands delineation is essential. If wetlands are present, federal (USACE) and state (DEQ) permits will be necessary, potentially requiring costly mitigation or significant setbacks, which could reduce the developable area of the 15.99-acre parcel.
  • Critical Habitat / Endangered Species Risk: The data indicates "None" for Critical Habitat within the vicinity, which is a significant positive. This minimizes the risk of lengthy environmental impact assessments or project delays due to protected species concerns.
  • Brownfield/Superfund Status: The property is noted as having "None within ~2 miles" for Brownfield/Superfund sites. This is positive as it eliminates contamination risks and associated remediation costs. However, it also means the project will not qualify for the IRA Brownfield bonus ITC adder, which is a missed incentive opportunity.
  • Chesapeake Bay Critical Area: Confirmed as "N/A (non-MD)", so this constraint is not applicable to the Henrico, VA site.
  • Pipeline Proximity Safety Considerations: "None within ~3 miles" for pipeline proximity is a major positive for safety. This significantly reduces the risk of explosion hazards, required safety setbacks, and complex permitting associated with high-pressure gas or hazardous liquid pipelines.

3. Grid Infrastructure & Interconnection

  • Nearest Substation & Transmission Line: The site boasts exceptional grid proximity. The "CHARLES CITY ROAD" substation is a mere 0.1 miles away with a Max Voltage of 230 kV. Furthermore, a 230kV transmission line (VIRGINIA ELECTRIC & POWER CO) is directly adjacent at 0.0 miles. This is a highly advantageous characteristic, significantly de-risking interconnection.
  • Recommended Interconnection Voltage: Given the immediate proximity to both a 230kV substation and a 230kV transmission line, a utility-scale interconnection at 230kV is highly feasible. For a distribution-scale project (≤5MW), it is more likely to interconnect at a lower distribution voltage (e.g., 34.5kV or 12.47kV) directly from the substation's distribution feeders, assuming available capacity. The "IX Voltage" is Unknown, requiring clarification from Dominion Energy Virginia. However, the proximity to high-voltage infrastructure provides flexibility for future expansion or larger projects.
  • Estimated Interconnection Cost Range & Timeline: The extremely short distance to the substation and transmission line suggests a significantly lower interconnection cost compared to typical projects. Costs for line extensions would be minimal. However, the primary cost driver will be substation upgrades (if required) and the Interconnection Agreement (IA) study process. We can estimate a range of $500k - $2M for a 5MW distribution-level connection, potentially higher for a direct 230kV transmission connection if significant substation work is needed. The timeline will be dictated by Dominion Energy Virginia's queue, typically 18-36 months from application to energization for a distribution-level project.
  • Utility-Specific IX Process & Queue Times: The interconnecting utility is VIRGINIA ELECTRIC & POWER CO (Dominion Energy Virginia). Dominion's interconnection process is known to be robust, with a multi-stage study process (Feasibility, System Impact, Facilities). Queue times can be substantial, and available capacity at the specific feeder or bus within the CHARLES CITY ROAD substation will be a critical determinant. Early engagement with Dominion is essential.
  • Likely Feeder Configuration: "POI Onsite" implies direct access. For a distribution-scale project, it would likely be a radial or networked feeder from the CHARLES CITY ROAD substation. Specific feeder details are Unknown and require a pre-application meeting or formal interconnection request.

4. Regulatory & Zoning Analysis

  • Authority Having Jurisdiction (AHJ): The AHJ is Henrico County, as the municipality is "Unincorporated".
  • Current Zoning for BESS Compatibility: The zoning is listed as "Vacant Land - Commercial-Vacant Land (Code: MIXE)" and "Zoning (Regrid): M-1C". M-1C (Light Industrial) zoning in Henrico County is generally favorable for industrial uses, including energy infrastructure like BESS. MIXE (Mixed-Use) could also be compatible, but M-1C is typically more straightforward. This is a positive indicator for BESS development.
  • Recommended Permitting Pathway: Given the M-1C zoning, a BESS project may be permitted either by-right (if explicitly listed as a permitted use) or more commonly, via a Conditional Use Permit (CUP) or Special Exception. A CUP process would involve public hearings and require demonstrating compliance with specific county criteria. This is the most likely pathway.
  • Known Setback Requirements: Specific setback requirements for BESS in Henrico County are Unknown. These will be crucial for site layout and determining the actual developable footprint. Typical setbacks can range from 50-200 feet from property lines, residential zones, or public roads.
  • State/County Regulations: Henrico County's Zoning Ordinance (Chapter 24) will govern the BESS project. Virginia also has state-level regulations for energy facilities, particularly regarding environmental impact and safety, but local zoning is often the primary hurdle for distribution-scale projects.
  • Moratorium or Restriction Risks: Any known moratoriums or restrictions on BESS development in Henrico County are Unknown. This requires direct verification with the county planning department. Some jurisdictions have implemented temporary moratoriums while developing specific BESS ordinances.

5. IRA/ITC Incentive Analysis

  • Opportunity Zone Eligibility: The property is designated "No" for Opportunity Zone eligibility. This means the project will not qualify for the additional 10% ITC adder associated with Opportunity Zones.
  • Energy Community Status: The property is designated "No" for Energy Community status. Consequently, the project will not receive the 10% ITC adder for being located in an Energy Community (e.g., brownfield site, coal closure area, fossil fuel employment loss area).
  • Low-Income Community Qualification: The property is designated "No" for Low-Income Community qualification. This means the project will not be eligible for the 10% or 20% ITC adder for serving low-income communities or being located within one.
  • Potential Cumulative ITC Adder Percentage: Based on the provided data, the cumulative ITC adder percentage for this site is 0%. This is a significant drawback, as these adders can substantially improve project economics. The project would only qualify for the base 30% ITC (assuming domestic content and prevailing wage/apprenticeship requirements are met).

6. BESS Score & Rationale

BESS Suitability Score: 72/100

  • Location (18/20): Excellent public road access and "Great" buildability. The 15.99 acres provide ample space for a distribution-scale BESS. No major topographical challenges are anticipated.
  • Grid Access (25/25): Outstanding. Direct proximity (0.1 mi) to a 230kV substation and 0.0 mi to a 230kV transmission line is a rare and highly valuable asset, significantly reducing interconnection costs and risks. This is the site's strongest attribute.
  • Environmental (8/15): Mixed. While there are no critical habitats, pipelines, or brownfield risks, the Unknown status of FEMA Flood Zone and Wetlands is a major concern. These unknowns introduce significant risk and potential for project delays or increased costs.
  • Regulatory (10/15): Favorable M-1C/MIXE zoning is a strong positive. However, the Unknown specific BESS compatibility, permitting pathway details (CUP likely), setback requirements, and potential moratoriums in Henrico County introduce uncertainty.
  • Incentives (5/15): Poor. The lack of eligibility for Opportunity Zone, Energy Community, or Low-Income Community adders results in a 0% cumulative ITC adder. This significantly impacts project economics compared to sites with these qualifications.
  • Buildability (6/10): "Great" buildability and "POI Onsite" are positive. However, the lack of specific "Buildable Acres" and the unknowns regarding wetlands/flood zones mean the actual usable footprint is still uncertain, hence not a perfect score.

7. Key Risks & Mitigants

  • Risk 1: Environmental Unknowns (FEMA Flood Zone & Wetlands)
    • Mitigant: Immediately commission a Phase I Environmental Site Assessment (ESA) followed by a detailed FEMA Flood Zone determination and a professional wetlands delineation. This is a critical go/no-go decision point.
  • Risk 2: Lack of IRA/ITC Adders
    • Mitigant: Conduct a thorough financial modeling exercise to assess project viability with only the base 30% ITC. Explore other potential state or local incentives (e.g., property tax abatements, grants) specific to Virginia or Henrico County that could partially offset the lack of federal adders.
  • Risk 3: Interconnection Specifics (Capacity & Queue)

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads