⚡ 2237 HUDSON RD

Dorchester, MD — Intake Report
📍 38.562334, -76.1068512 📐 144.17 acres 🏷️ APN: 7180438 🔌 e6416185-0b1a-4900-acfa-445340997866 📅 Generated May 12, 2026 12:27 PM 🆔 MD004084
Go
BESS Score: /10 Buildable: ac Nearest Sub: West Cambridge (0.4 mi) Zoning: Agricultural/Rural - Agricultural / Rural (General)
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

TRAVERS HAROLD W SR
144.17
7180438
Agricultural/Rural - Agricultural / Rural (General) (-)
Battery Energy Storage
Dorchester
24019
143.95 ACRES S/S MD. RT. 343 CAMBRIDGE

⚡ Infrastructure

e6416185-0b1a-4900-acfa-445340997866
69 kV
West Cambridge
0.4 mi
69 kV kV
None within ~3 miles
Public
POI Onsite
Great

🌊 Environmental

Loading...
Loading...
No
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Loading from layers...

📊 Assessment

Go
/10

🤖 AI Site Assessment — Gemini Deep Research

Site Access & Topography

The property at 2237 HUDSON RD, Dorchester County, MD, benefits from Public Road Access, which is a significant advantage for BESS development. This typically ensures unencumbered legal access for construction and operational activities without the need to negotiate private road easements. Furthermore, the data indicates POI Onsite (Point of Interconnection Onsite), which is an exceptional characteristic, implying direct access to the interconnection point from the property itself. This minimizes the need for costly and complex off-site interconnection infrastructure and associated easements.

With a total area of 144.17 acres and a zoning of "Agricultural/Rural (General)", the terrain is highly likely to be relatively flat and open, characteristic of agricultural land in Dorchester County, Maryland. This flat topography is ideal for BESS construction, reducing grading requirements and associated costs. The large parcel size provides ample space for equipment setbacks, fire breaks, and potential future expansion.

Given the public road access, likely flat terrain, and the substantial acreage, heavy equipment such as large transformers, battery containers, and construction machinery should have excellent access to the site. The "Buildability: Great" assessment further supports this conclusion. There are no immediate access easement concerns noted, but a detailed survey will be required to confirm the exact property boundaries and ensure the POI is indeed fully within the property or has a dedicated easement.

Environmental Constraints

Several critical environmental data points are currently Unknown, which presents significant risks. The FEMA Flood Zone designation is a major gap; BESS facilities are highly sensitive to flooding, and siting within a high-risk flood zone (e.g., AE, VE) would necessitate extensive and costly flood mitigation measures or render the site unsuitable. Similarly, the presence of Wetlands is unknown. Maryland has stringent wetland protection regulations, and the presence of jurisdictional wetlands could trigger complex permitting, require significant setbacks, or even preclude development on portions of the site.

Positively, the property shows None for Critical Habitat, Protected Areas, Brownfield/Superfund status within 2 miles, and Gas Wells Nearby within 2 miles. This eliminates several common environmental hurdles and associated permitting complexities or safety concerns. The absence of Brownfield/Superfund status means no environmental remediation costs, but also no IRA brownfield bonus. Crucially, the site is designated as No for Chesapeake Bay Critical Area, which is a significant advantage in Maryland, as development within this highly regulated zone faces extremely strict impervious surface limits, buffer requirements, and permitting challenges. Finally, No Pipeline Proximity within 3 miles mitigates safety risks and potential easement conflicts.

Actionable Insight: Immediate priority must be given to commissioning a Phase I Environmental Site Assessment (ESA), a wetland delineation study, and a precise FEMA flood zone determination to quantify these critical unknowns.

Grid Infrastructure & Interconnection

The grid infrastructure at this site is a major strength. The Nearest Substation, West Cambridge, is only 0.4 miles away with a Max Voltage of 69 kV. This extremely close proximity to a transmission-level substation is ideal for BESS projects, significantly reducing interconnection costs and construction timelines for the gen-tie line. The specified IX Voltage is 69 kV, confirming a transmission-level interconnection.

The data states "Nearest Transmission Line: None within ~3 miles," which appears to contradict the 69 kV substation and IX voltage. It is highly probable that the 69 kV substation is connected to a 69 kV transmission line, and the data point might refer to a *separate* transmission line not directly associated with the substation. For a 69 kV interconnection, the project will connect directly into the substation's 69 kV bus or a dedicated breaker.

Given the short distance (0.4 miles) to a 69 kV substation, the interconnection cost range for the gen-tie line itself should be relatively low, likely in the range of $500,000 to $1.5 million, depending on specific substation upgrades required. However, the overall interconnection cost will also depend on network upgrade requirements identified during the utility's System Impact Study (SIS). The timeline for a 69 kV interconnection in Maryland (likely Delmarva Power, an Exelon company, given Dorchester County) can range from 24 to 48 months, primarily driven by the utility's interconnection queue and study processes (Feasibility, System Impact, Facilities).

The Interconnecting Utility is identified by a UUID ("e6416185-0b1a-4900-acfa-495340997866"), which is not a recognizable name. This requires immediate verification. However, based on the location in Dorchester County, MD, the utility is almost certainly Delmarva Power. Delmarva Power's interconnection process follows PJM's (Pennsylvania-New Jersey-Maryland Interconnection) queue, which is known for lengthy study timelines. The likely feeder configuration is a direct connection to the 69 kV transmission bus within the West Cambridge substation.

Regulatory & Zoning Analysis

The Authority Having Jurisdiction (AHJ) is "Found (unnamed)", which needs clarification but is almost certainly Dorchester County, MD, specifically its Planning & Zoning Department. The current zoning is Agricultural/Rural (General) (Code: -) and also noted as "R" (Regrid). This zoning is generally not "by-right" for utility-scale BESS facilities in Maryland counties.

Therefore, the recommended permitting pathway will almost certainly be a Conditional Use Permit (CUP) or Special Exception. This process involves public hearings, detailed site plan review, and discretionary approval by the County Planning Commission and/or Board of Appeals. This pathway is more complex, time-consuming, and carries higher risk than a by-right approval.

Known setback requirements for BESS in this jurisdiction are "Unknown." However, Dorchester County, like many Maryland counties, will likely have specific setback requirements from property lines, residential structures, and public roads for industrial-type uses or facilities requiring a CUP. These can range from 50 to 200 feet or more, depending on the specific ordinance. Maryland state regulations (e.g., COMAR) may also influence local requirements, particularly regarding fire safety and environmental protection.

There are no known moratorium or restriction risks, but this requires verification with the County. The discretionary nature of a CUP/Special Exception process means that local opposition, if significant, could pose a substantial risk to project approval.

Actionable Insight: Direct engagement with Dorchester County Planning & Zoning is crucial to understand specific BESS ordinances, setback requirements, and the exact CUP/Special Exception process.

IRA/ITC Incentive Analysis

The property's eligibility for key Inflation Reduction Act (IRA) Investment Tax Credit (ITC) adders is unfortunately limited based on the provided data:

  • Opportunity Zone eligibility: No - This means the 10% ITC adder for projects located in Opportunity Zones is not applicable.
  • Energy Community status: No - This means the 10% ITC adder for projects located in Energy Communities (e.g., brownfield sites, coal closure areas, fossil fuel employment areas) is not applicable.
  • Low-Income Community qualification: No - This means the 10% or 20% ITC adder for projects located in Low-Income Communities or benefiting low-income households is not applicable.

Based on these factors, the potential cumulative ITC adder percentage is 0%. This is a significant drawback for the project's financial viability, as these adders can substantially improve project economics. The project would only qualify for the base ITC (currently 30% if prevailing wage and apprenticeship requirements are met) without any additional bonuses.

Actionable Insight: While the current data indicates no eligibility, a more granular analysis of census tracts might be warranted to confirm Low-Income Community status, as definitions can be complex. However, without these adders, the project's financial model will need to be robust to justify development.

BESS Score & Rationale

BESS Suitability Score: 68/100

  • Location (18/20): Excellent. 144.17 acres provides ample space. Public road access and POI onsite are ideal for buildability and cost efficiency. Likely flat, open terrain.
  • Grid Access (23/25): Outstanding. Proximity of 0.4 miles to a 69 kV substation is nearly perfect, minimizing gen-tie costs and maximizing grid injection potential. The 69 kV interconnection voltage is suitable for utility-scale projects.
  • Environmental (8/15): Moderate-to-Low. While many positive factors exist (no critical habitat, pipelines, Chesapeake Critical Area, or brownfield risk), the "Unknown" status for FEMA Flood Zone and Wetlands are critical gaps that introduce significant, unquantified risks and potential costs.
  • Regulatory (7/15): Low. Agricultural/Rural zoning is a major hurdle, requiring a Conditional Use Permit (CUP) which is a discretionary and often lengthy process. Unknown AHJ specifics and setback requirements add to the uncertainty and risk.
  • Incentives (3/15): Very Low. The complete lack of eligibility for IRA ITC adders (Opportunity Zone, Energy Community, Low-Income Community) significantly impacts project economics and competitiveness.
  • Buildability (9/10): Excellent. "Great" buildability, large parcel size, public access

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.