⚡ 215 RICKARDS ST

Cecil, MD — Intake Report
📍 39.4021236, -75.8721382 📐 5.64 acres 🏷️ APN: 801001043 🔌 📅 Generated May 12, 2026 11:47 AM 🆔 MD002492
Go
BESS Score: 53/10 Buildable: 5.41 ac Nearest Sub: EARLVILLE (2.441 miles) Zoning: Vacant Land - Residential-Vacant Land
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

ALAN MCCARTHY
5.64
801001043
Vacant Land - Residential-Vacant Land (R1)
Battery Energy Storage
Cecil
24015
6.124 ACRES RICKARDS STREET CECILTON

⚡ Infrastructure

EARLVILLE
2.441 miles
0 kV kV
None within ~3 miles

🌊 Environmental

Loading...
Loading...
No
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Cecil
County
Loading from layers...

📊 Assessment

Go
53/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

The property, identified as 215 RICKARDS ST in Cecil County, MD, is listed as "Vacant Land - Residential-Vacant Land (Code: R1)" with a total of 5.64 acres, of which 5.41 acres are designated as buildable. This high ratio of buildable to total acreage (approximately 96%) suggests a relatively flat and unencumbered terrain, which is highly favorable for BESS construction, minimizing grading and earthwork costs.

However, critical information regarding "Road Access" and "POI Access" is currently unknown. This is a significant gap in our diligence. Without knowing the quality, width, and load-bearing capacity of the access roads leading to the site, it is impossible to definitively assess the feasibility of delivering heavy equipment such as transformers, switchgear, and battery containers. These components often require specialized heavy-haul trucks and can be restricted by bridge weight limits, tight turns, or unpaved/poorly maintained roads.

Actionable Insights: A priority site visit is required to physically inspect the existing road infrastructure and potential access points. We must verify if the property has direct frontage on a public road or if an access easement would be required. If an easement is needed, its terms, cost, and legal feasibility must be thoroughly investigated. The generally flat topography is a positive, but the unknown access is a major buildability risk.

2. Environmental Constraints

Several key environmental factors present a mixed picture for this site. Positively, the property is not within the Chesapeake Bay Critical Area, which avoids a complex layer of environmental review and stringent development restrictions. There are also no identified critical habitats or endangered species risks, no brownfield/superfund sites within 2 miles (meaning no remediation costs, but also no IRA brownfield bonus), and no pipeline proximity safety concerns within 3 miles. These factors reduce potential permitting delays and environmental mitigation costs.

However, two critical environmental data points are currently "Unknown": the FEMA Flood Zone designation and the presence of Wetlands. These are significant red flags.

  • FEMA Flood Zone: Siting a BESS within a 100-year floodplain (Zone AE or VE) would necessitate elevated equipment, extensive floodproofing measures, and potentially higher insurance premiums, significantly increasing project costs and complexity.
  • Wetlands: The presence of jurisdictional wetlands would trigger federal (USACE Section 404) and state (MDE) permitting, requiring avoidance, minimization, or costly mitigation. Setback requirements from wetlands can also reduce the effective buildable area.

Actionable Insights: Immediate environmental due diligence is required. This includes ordering a Phase I Environmental Site Assessment (ESA) to identify potential environmental liabilities, a FEMA flood plain determination, and a preliminary wetland delineation. These steps are critical go/no-go decision points.

3. Grid Infrastructure & Interconnection

The nearest substation, EARLVILLE, is located 2.441 miles from the site. This distance is manageable for a distribution-scale BESS project (typically ≤5MW), keeping interconnection costs within a reasonable range. However, the "Max Voltage: 0 kV kV" for the substation is clearly an error or placeholder and represents a critical data gap. We need to verify the actual voltage class (e.g., 12.47kV, 34.5kV) to determine the appropriate interconnection voltage and available capacity.

The absence of any transmission lines within 3 miles strongly suggests that this project would pursue a distribution-level interconnection. The "Interconnecting Utility" and "IX Voltage" are also currently unknown. Given Cecil County, MD, the most likely interconnecting utility is Delmarva Power (DPL), a subsidiary of Exelon.

Recommended Interconnection Voltage: Based on the distance to the substation and lack of transmission, a distribution-level interconnection (e.g., 12.47kV or 34.5kV, depending on the substation's actual voltage) is recommended.

Estimated Interconnection Cost & Timeline: Assuming a 2.441-mile distribution line extension, costs could range from $1.5M to $3M+, depending on terrain, road crossings, and required upgrades at the substation. The timeline for DPL's interconnection process typically involves a pre-application, feasibility study, system impact study, and facilities study, which can collectively take 18-36 months, excluding construction. DPL's queue times can be substantial, requiring early engagement.

Actionable Insights: Immediately identify the specific interconnecting utility and initiate pre-application discussions to confirm the substation's actual voltage, available capacity on the feeder, and typical queue times. A detailed interconnection study scope will be required.

4. Regulatory & Zoning Analysis

The most significant regulatory hurdle for this site is its current zoning: "Vacant Land - Residential-Vacant Land (Code: R1)". R1 zoning is typically reserved for single-family residential development and is highly restrictive for industrial or utility-scale uses like a BESS. This is a major red flag.

The "Municipality / AHJ: Found (unnamed)" is vague, but the "Regrid Zoning: Town" suggests a specific town within Cecil County. Identifying this specific municipality is paramount, as local zoning ordinances vary significantly.

Recommended Permitting Pathway: Given R1 zoning, a "by-right" permitting pathway is highly improbable. The most likely pathways would be:

  • Conditional Use Permit (CUP) / Special Exception (SUP): This would require demonstrating that the BESS meets specific conditions and criteria outlined in the zoning ordinance, often involving public hearings and discretionary approval by the planning commission or board of appeals.
  • Variance: If the BESS cannot meet specific dimensional or use requirements, a variance might be sought, which is typically difficult to obtain and requires demonstrating undue hardship.
  • Rezoning: This is the most challenging and time-consuming pathway, requiring a legislative change to the zoning map, often with significant public opposition.

Setback Requirements: Specific setback requirements for BESS facilities in this jurisdiction are unknown but will be critical. Residential zoning typically has stringent setbacks from property lines and residential structures, which could significantly impact the usable area on the 5.64-acre parcel. Maryland state regulations (e.g., COMAR 20.61.01 for energy generation facilities) may also apply, but local zoning is usually the primary determinant for distribution-scale projects.

Moratorium/Restriction Risks: There is no data on potential moratoriums or restrictions. However, given the residential zoning, community opposition to an industrial facility could lead to such risks.

Actionable Insights: Immediately identify the specific municipality and obtain a copy of their zoning ordinance. Conduct a thorough review to understand the exact requirements for BESS in R1 zones or potential pathways for approval. Early engagement with the AHJ (e.g., pre-application meeting) is crucial to gauge their receptiveness and preferred permitting path. This is a significant go/no-go factor.

5. IRA/ITC Incentive Analysis

Based on the provided data, this site does not qualify for any of the major Inflation Reduction Act (IRA) Investment Tax Credit (ITC) adders:

  • Opportunity Zone Eligibility: No

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.