⚡ 30744 PERRY RD

Somerset, MD — Intake Report
📍 38.1643801, -75.6878034 📐 6.78 acres 🏷️ APN: 2015000562 🔌 Delmarva Power 📅 Generated May 12, 2026 04:29 PM 🆔 MD000056
Go
BESS Score: 79/10 Buildable: 2.12 ac Nearest Sub: Kings Creek (0.05 miles) Zoning: Residential - Rural/Agricultural Residence
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

JOHN BARNES
6.78
2015000562
Residential - Rural/Agricultural Residence (I-2)
Battery Energy Storage
Somerset
24039
6.547 AC-PL 32/63 N/S PERRY RD SE/PR ANNE

⚡ Infrastructure

Delmarva Power
Kings Creek
0.05 miles
138 kV kV
138kV at 0.1 mi (DELMARVA POWER)
16 ft
All areas are prime farmland
Private
POI Onsite
Great

🌊 Environmental

Loading...
Loading...
No
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Somerset
County
Loading from layers...

📊 Assessment

Go
79/10

🤖 AI Site Assessment — Gemini Deep Research

Site Diligence Analysis: 30744 PERRY RD, Somerset, MD

As a senior BESS site evaluation analyst for Sunland America Corp, I have performed a comprehensive diligence analysis for the property located at 30744 PERRY RD in Somerset County, Maryland. This analysis evaluates the site's suitability for a distribution-scale (≤5MW) or utility-scale Battery Energy Storage System, considering all critical development factors.

1. Site Access & Topography

  • Road Access Quality and Equipment Delivery Feasibility: The property's road access is explicitly stated as Private. This is a significant concern. While the "Buildability: Great" indicator suggests favorable terrain for construction, a private road implies potential limitations on width, weight capacity, and surface quality, which are critical for delivering heavy equipment such as transformers, battery containers, and construction machinery. Upgrades to the private road may be necessary, incurring substantial costs and requiring negotiations with the road owner(s) or securing a perpetual access easement.
  • Likely Terrain Characteristics: The "Buildability: Great" assessment, coupled with the rural/agricultural zoning, suggests relatively flat or gently sloping terrain, ideal for BESS construction without extensive grading. The 6.78 total acres, with 2.12 buildable acres, indicates sufficient space for the BESS footprint, associated infrastructure, and required setbacks.
  • Heavy Equipment Access: Access for heavy equipment (e.g., 100-ton transformers, 40-foot battery containers) is highly questionable due to the private road status. A detailed survey of the private road's condition, width, turning radii, and load-bearing capacity is immediately required. Without a robust, publicly maintained road, the logistical challenges and costs associated with equipment delivery could be prohibitive.
  • Access Easement Concerns: Given the private road, securing a legal, perpetual, and unencumbered access easement from the current owner(s) of the private road is paramount. This easement must explicitly permit heavy vehicle traffic, construction activities, and ongoing operational access for maintenance and emergencies. This process can be lengthy and complex, potentially involving multiple landowners.

2. Environmental Constraints

  • FEMA Flood Zone Designation: The FEMA Flood Zone is currently Unknown. This is a critical data gap. BESS facilities must be sited outside of 100-year floodplains (Zone AE or A) or engineered with significant flood mitigation measures, which add considerable cost and complexity. A full flood plain analysis is required.
  • Wetlands Presence and Setback Requirements: Wetlands presence is also Unknown. This is another major environmental risk. Wetlands can trigger federal (USACE Section 404) and state (MDE) permitting, requiring extensive delineation, mitigation, and significant setbacks, which could reduce the already limited 2.12 buildable acres.
  • Critical Habitat / Endangered Species Risk: The data indicates None for Critical Habitat within the vicinity. This is a positive finding, reducing the risk of project delays or costly mitigation measures related to protected species.
  • Brownfield/Superfund Status: The property is designated as None within ~2 miles for Brownfield/Superfund sites. This eliminates environmental contamination risks associated with such sites but also means the project will not qualify for the IRA Brownfield bonus ITC adder.
  • Chesapeake Bay Critical Area Implications: The property is explicitly noted as No within the Chesapeake Bay Critical Area. This is a significant advantage, as it avoids stringent development restrictions, impervious surface limits, and enhanced stormwater management requirements typically associated with projects in the Critical Area.
  • Pipeline Proximity Safety Considerations: There are None within ~3 miles. This is favorable, as it eliminates safety concerns, setback requirements, and potential permitting complexities associated with siting BESS near high-pressure gas or hazardous liquid pipelines.

3. Grid Infrastructure & Interconnection

  • Nearest Substation: The Kings Creek Substation is an exceptional 0.05 miles away, with a Max Voltage of 138 kV. This extremely close proximity is a major advantage for interconnection.
  • Nearest Transmission Line: A 138kV DELMARVA POWER transmission line is located at an outstanding 0.1 mi. This direct access to high-voltage infrastructure is ideal.
  • Recommended Interconnection Voltage: Given the immediate proximity to a 138kV substation and transmission line, the most logical and efficient interconnection voltage would be 138kV (transmission-level). While distribution-scale projects often connect at lower voltages (e.g., 34.5kV or 12.47kV), the direct access to 138kV makes a transmission-level interconnection highly attractive, potentially offering greater capacity and fewer constraints, assuming the project size warrants it. However, a distribution-level interconnection should also be evaluated if the project is strictly ≤5MW and Delmarva Power has suitable distribution feeders nearby.
  • Estimated Interconnection Cost Range and Timeline: The extremely short distance to both substation and transmission line suggests a significantly lower interconnection cost compared to sites requiring extensive new line construction. Costs would primarily involve a new substation bay, protection upgrades, and a short gen-tie line. A preliminary estimate could range from $1M - $3M for a transmission-level connection, but this is highly dependent on Delmarva Power's specific requirements and existing infrastructure. The timeline could be 18-36 months, assuming a relatively smooth queue process, but this requires utility-specific verification.
  • Utility-Specific IX Process and Typical Queue Times: The interconnecting utility is Delmarva Power. Their specific interconnection process (e.g., FERC Order 2003/2222 compliance, study phases, typical queue length, and study costs) is unknown and requires immediate investigation. Delmarva Power's queue times can vary significantly based on regional demand and system constraints.
  • Likely Feeder Configuration: Given the direct proximity to the Kings Creek 138kV substation, the likely configuration would be a direct connection to the 138kV bus or a very short, dedicated gen-tie line to the transmission system. If a distribution-level connection is pursued, the feeder configuration would depend on the nearest available distribution circuit from the substation.

4. Regulatory & Zoning Analysis

  • Authority Having Jurisdiction (AHJ) and Type: The AHJ is Unincorporated (Somerset County, MD). This means the county government is the primary permitting authority, which can sometimes be more predictable than complex municipal jurisdictions, but still requires thorough understanding of county ordinances.
  • Current Zoning for BESS Compatibility: The current zoning is Residential - Rural/Agricultural Residence (Code: I-2). This is a severe impediment. BESS facilities are typically considered industrial or utility uses and are rarely permitted by-right in residential or agricultural zones. This zoning is a major red flag.
  • Recommended Permitting Pathway: Given the I-2 zoning, a "by-right" pathway is highly improbable. The most likely pathways would be:
    • Conditional Use Permit (CUP) or Special Exception: This is the most common pathway for BESS in incompatible zones, requiring a public hearing and demonstrating the project meets specific conditions and does not negatively impact the surrounding area.
    • Zoning Amendment/Rezone: This is a more challenging and time-consuming process, requiring a legislative change to the zoning map or text, often with significant public opposition.
    • Variance: Less likely for a primary use, usually for minor deviations.
    The CUP/Special Exception pathway is the most feasible but will require significant community engagement and a robust application.
  • Known Setback Requirements: Specific setback requirements for BESS in Somerset County's I-2 zone are Unknown and must be thoroughly researched. Typical BESS setbacks can range from 50-500 feet from property lines, residential structures, and public roads, which could significantly impact the 2.12 buildable acres.
  • State/County Regulations: Maryland does not have a statewide BESS siting law, deferring to local jurisdictions. Therefore, Somerset County's zoning ordinances and comprehensive plan are the primary regulatory documents. Specific county code sections pertaining to "utility uses," "heavy industrial," or "energy facilities" must be identified.
  • Moratorium or Restriction Risks: Any known moratoriums or restrictions on BESS development in Somerset County are Unknown. This needs immediate verification, as some rural counties have implemented temporary bans or strict ordinances due to public concerns.

5. IRA/ITC Incentive Analysis

  • Opportunity Zone Eligibility: The property is designated as No for Opportunity Zone eligibility. This means the project will not qualify for the additional 10% ITC adder associated with Opportunity Zones.
  • Energy Community Status: The property is designated as No for Energy Community status. This eliminates the potential for the 10% ITC adder available for projects located in Energy Communities (e.g., brownfield sites, coal closure areas, or areas with significant fossil fuel employment).
  • Low-Income Community Qualification: The property is designated as No for Low-Income Community qualification. This means the project will not be eligible for the 10% or 20% ITC adder available for projects serving low-income communities.
  • Potential Cumulative ITC Adder Percentage: Based on the provided data, the cumulative ITC adder percentage for this site is 0%. The project would only qualify for the base 30% ITC (assuming prevailing wage and apprenticeship requirements are met), without any additional adders.

6. BESS Score & Rationale

Overall BESS Suitability Score: 55/100

  • Location (0-20): 12/20
    • Rationale: Excellent proximity to the grid (substation and transmission line) is a major positive. However, the private road access introduces significant logistical and cost challenges, reducing the score.
  • Grid Access (0-25): 24/25
    • Rationale: Unparalleled proximity (0.05 miles to substation, 0.1 miles to transmission) to high-voltage infrastructure. This is the site's strongest attribute, promising lower interconnection costs and potentially faster timelines, pending Delmarva Power's queue.
  • Environmental (0-15): 7/15
    • Rationale: No critical habitat, brownfield, pipelines, or Chesapeake Bay Critical Area is positive. However, the "Unknown" status for FEMA Flood Zone and Wetlands represents significant, unquantified risks that could severely impact buildability or cost.
  • Regulatory (0-15): 3/15
    • Rationale: The I-2 Residential - Rural/Agricultural zoning is a major hurdle, making "by-right" permitting highly unlikely. A Conditional Use Permit or rezone will be required, which is a lengthy, costly, and uncertain process, especially in a rural county potentially sensitive to industrial development.
  • Incentives (0-15): 0/15
    • Rationale: The site does not qualify for any of the IRA ITC adders (Opportunity Zone, Energy Community, Low-Income Community), resulting in 0% additional ITC.
  • Buildability (0-10): 9/10

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.