⚡ 106 E LONGMEADOW RD

Hampden County, MA — Intake Report
📍 42.058262, -72.4496302 📐 3.96 acres 🏷️ APN: 120 12_81_0 🔌 📅 Generated June 25, 2026 02:02 PM 🆔 MA006601
BESS Score: /10 Buildable: ac Nearest Sub: HAMPDEN (1.0 mi) Zoning: Commercial (Retail) - Commercial (General)
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

HENRY DAVID J
3.96
120 12_81_0
Commercial (Retail) - Commercial (General) (-)
Hampden County
25013
-

⚡ Infrastructure

HAMPDEN
1.0 mi
115 kV
345kV at 0.6 mi (CONNECTICUT LIGHT & POWER CO)
236 ft
Farmland of statewide importance
🔴 203 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Hampden

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

Site Access & Topography

The subject property at 106 E Longmeadow Rd, Hampden, MA, appears to have direct frontage on East Longmeadow Road, a paved, two-lane county road. Based on aerial imagery, this road seems suitable for standard construction traffic, including dump trucks and concrete mixers. However, the delivery of oversized and overweight equipment, such as a main power transformer (MPT) and prefabricated battery enclosures, requires further diligence. A route survey would be necessary to confirm the absence of restrictive vertical clearances, tight turning radii, or weight-limited bridges between the nearest major highway (e.g., I-90) and the site.

The topography of the 3.96-acre parcel appears to be relatively flat with a gentle slope, which is advantageous for minimizing civil work and grading costs. The parcel is partially wooded, and clearing and grubbing will be required to create a suitable pad for the BESS compound. The key challenge will be establishing a construction entrance off East Longmeadow Road capable of handling heavy haul trucks. We must verify that no access easements are required from adjacent parcels. A preliminary title report is necessary to confirm the property has unencumbered legal access and to identify any existing utility or access easements that could conflict with the proposed site layout.

Environmental Constraints

The environmental profile presents several critical unknowns that must be addressed immediately.

  • FEMA Flood Zone: The flood zone designation is currently unknown. Any designation other than Zone X (minimal flood risk) would be a significant risk. Siting critical infrastructure within a Special Flood Hazard Area (e.g., Zone A, AE) would trigger extensive and costly mitigation requirements, such as elevating all equipment above the Base Flood Elevation, potentially rendering the project economically unviable. This requires immediate verification via the FEMA Flood Map Service Center.
  • Wetlands: The presence of wetlands is also unknown. Massachusetts has stringent wetland protection regulations under the Massachusetts Wetlands Protection Act, enforced by the local Conservation Commission. Any identified wetlands on or near the parcel would necessitate significant setbacks (typically 100 feet or more), which could severely constrain the buildable area on this already small 3.96-acre lot. A wetland delineation study by a certified professional is a critical next step.
  • Habitat & Protected Species: The data indicates no critical habitat or protected areas on site, which is a positive initial finding. This reduces the risk of lengthy and complex consultations with state (MA DFW) or federal (USFWS) wildlife agencies.
  • Contamination Status: The site is not listed as a brownfield or superfund site. While this avoids potential remediation liabilities, it also means the project is ineligible for the 10% ITC "Brownfield" adder under the Inflation Reduction Act (IRA), which is a notable disadvantage to the project's financial model.
  • Pipeline Proximity: The absence of major gas pipelines within a 3-mile radius is a significant safety and layout advantage, eliminating the need for specialized setbacks and safety protocols associated with high-pressure pipeline adjacencies.

Grid Infrastructure & Interconnection

The grid infrastructure presents a mixed but potentially viable opportunity. The primary point of interconnection (POI) target is the HAMPDEN substation, located approximately 1.0 mile from the site. While the substation's max voltage is 115 kV (transmission level), it is highly probable that it also contains a distribution-level bus (e.g., 13.2 kV or 23 kV), which would be the appropriate voltage for a distribution-scale (≤5MW) BESS project.

The 345 kV transmission line located 0.6 miles away is not a feasible POI for a project of this scale due to the prohibitively high cost of a 345 kV switchyard and associated protection equipment.

Our interconnection strategy must focus on the distribution system out of the HAMPDEN substation. The 1.0-mile distance is a significant concern, as it will require a new dedicated feeder line extension, likely via overhead poles. A rough, preliminary cost estimate for this extension could range from $750,000 to $1.5 million, depending on terrain, road crossings, and utility requirements. The interconnecting utility is not specified but is likely Eversource in this region. The ISO New England (ISO-NE) interconnection process is notoriously complex and slow. Even for a distribution-level project, queue times for studies can exceed 18-24 months before an Interconnection Service Agreement (ISA) is executed. Immediate submission of an interconnection application is critical to enter the queue and obtain a cost estimate from the utility.

Regulatory & Zoning Analysis

The Authority Having Jurisdiction (AHJ) is the Town of Hampden, MA. The property is zoned "Commercial (C)". This zoning designation is a critical uncertainty. BESS facilities are a relatively new use case and are often not explicitly defined in municipal zoning codes. It is unlikely that BESS is a "by-right" use in a Commercial zone.

The most probable permitting pathway will be a Special Permit (or Special Exception) from the Hampden Planning Board or Zoning Board of Appeals. This process involves public hearings and discretionary approval, introducing significant timeline risk and uncertainty. We must research the Town of Hampden's specific zoning bylaws to determine if BESS is addressed and to identify applicable requirements for setbacks, screening, noise limits (a key concern for BESS), and safety (alignment with NFPA 855 standards). Massachusetts has a reputation for challenging local permitting environments, and community opposition can be a major obstacle. A pre-application meeting with town staff is essential to gauge their familiarity with and disposition towards BESS projects.

IRA/ITC Incentive Analysis

The project's eligibility for federal incentives under the IRA is extremely weak, which presents a major challenge to its financial viability.

  • Opportunity Zone: No. Not eligible for the 10% bonus.
  • Energy Community: No. Not eligible for the 10% bonus.
  • Low-Income Community: No. Not eligible for the 10% bonus under the §48(e) program.

As a result, the project is only eligible for the base 30% Investment Tax Credit (ITC), assuming prevailing wage and apprenticeship (PWA) requirements are met. Without PWA compliance, the credit drops to a mere 6%. This lack of any "stackable" ITC adders puts the project at a significant financial disadvantage compared to projects sited in more favorable incentive zones. The project economics must be robust enough to succeed with only the base 30% ITC.

BESS Score & Rationale

Overall BESS Suitability Score: 49 / 100

  • Location (12/20): The site is on a county road and is relatively close to a substation. However, its small size and proximity to other commercial/residential properties could create land use conflicts.
  • Grid Access (15/25): Proximity to a 115kV substation is a major plus, but the 1.0-mile distance to interconnect at distribution voltage is a significant cost and feasibility hurdle. The actual feeder capacity is unknown.
  • Environmental (10/15): The site scores well on known factors (no critical habitat, no contamination). However, the score is penalized due to the critical unknowns of flood zone and wetlands, which could be fatal flaws.
  • Regulatory (8/15): Commercial zoning is not ideal and creates permitting uncertainty. The likely need for a Special Permit in a Massachusetts town presents a substantial risk to the project timeline and outcome.
  • Incentives (2/15): This is the project's weakest attribute. Ineligibility for

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.