⚡ LOMBARD RD

Hampden County, MA — Intake Report
📍 42.1690507, -72.5303736 📐 46.63 acres 🏷️ APN: 061 0270_00006 🔌 📅 Generated June 25, 2026 08:13 AM 🆔 MA005563
BESS Score: /10 Buildable: ac Nearest Sub: SHAWINIGAN SWITCHING STATION (0.8 mi) Zoning: Vacant Land - Private Preserve, Open Space-Vacant Land (Forest L
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

LOMBARDZ LLC
46.63
061 0270_00006
Vacant Land - Private Preserve, Open Space-Vacant Land (Forest L (8)
Hampden County
25013
-

⚡ Infrastructure

SHAWINIGAN SWITCHING STATION
0.8 mi
115 kV
345kV at 0.3 mi (NOT AVAILABLE)
158 ft
Not prime farmland
🔴 431 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
1 site(s) within ~2 mi

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Loading from layers...

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

Road Access & Equipment Delivery: The property is located on Lombard Rd in Chicopee, MA. A preliminary desktop review indicates that Lombard Road is a local, two-lane paved road. However, the specific parcel appears to be set back from the road and may only be accessible via an unpaved track or easement. The quality of this access point is unknown and is a critical risk. Requires Verification: A site visit is mandatory to confirm if Lombard Rd can support heavy truck traffic (80,000+ lbs) and to assess the condition of any access drive.

Terrain Characteristics: The current land use is designated as "Forest Land," which strongly suggests the site is undeveloped and likely features uneven, wooded terrain. Significant tree clearing, grading, and civil work will be required to create a level pad for the BESS compound, switchgear, and transformer. This will add considerable cost and time to the project construction phase. The parcel's topography must be professionally surveyed to determine the extent of earthwork needed.

Heavy Equipment Feasibility: Access for heavy equipment, including cranes for setting transformers and battery containers, is a major concern. The ability to get a lowboy trailer carrying a 50-ton transformer or a 40-foot battery container to the site depends entirely on the unverified access drive and whether there are any sharp turns, weak culverts, or low-hanging utility lines along the route from the main highway. The current information is insufficient to confirm feasibility.

Easement Concerns: The parcel appears landlocked or semi-landlocked from the main road. An access easement across an adjacent property may be required. Requires Verification: A title search must be conducted to confirm the existence, width, and terms of any deeded access easements. If none exist, negotiating and purchasing a new easement would be a significant project hurdle.

2. Environmental Constraints

FEMA Flood Zone: The FEMA flood zone designation is listed as "Unknown." This is a critical data gap. If the site is located within a 100-year floodplain (e.g., Zone AE), it could render the site undevelopable or require all equipment to be elevated above the Base Flood Elevation, dramatically increasing civil engineering and construction costs. This must be determined immediately via the FEMA Flood Map Service Center.

Wetlands: The presence of wetlands is "Unknown." Given the forested nature of the site in Massachusetts, there is a high probability of state or federally jurisdictional wetlands, vernal pools, or streams being present. Development is prohibited within wetlands, and significant setbacks (typically 25-100 feet or more) are required by the Chicopee Conservation Commission under the Massachusetts Wetlands Protection Act. A formal Wetland Delineation by a certified professional is a mandatory next step.

Critical Habitat / Endangered Species: The data indicates no known critical habitat on site, which is a positive initial finding. However, this should be confirmed through the Massachusetts Natural Heritage & Endangered Species Program (NHESP) database to ensure no state-listed species or priority habitats are impacted.

Brownfield/Superfund Status: There is one Superfund/Brownfield site within two miles, but the subject parcel itself is not identified as one. This presents more of a risk than an advantage. The IRA 10% Brownfield tax credit adder only applies if the project is built *on* a qualifying brownfield site. The proximity of another contaminated site could trigger complexities during a Phase I Environmental Site Assessment (ESA), potentially requiring a more in-depth Phase II ESA to rule out migrating contamination. The likelihood of qualifying for the IRA bonus here is very low.

Pipeline Proximity: The absence of major gas pipelines within three miles is a significant safety and layout advantage, eliminating concerns related to pipeline operator easements, setbacks, and explosion risks.

3. Grid Infrastructure & Interconnection

Nearest Substation & Voltage: The nearest facility is the Shawinigan Switching Station (0.8 miles, 115 kV). This is a critical finding. A 115 kV switching station is a high-voltage transmission asset, not a distribution substation. For a distribution-scale project (≤5MW), this is a fundamental mismatch. Interconnecting at transmission voltage is vastly more complex, expensive, and time-consuming than a typical distribution connection.

Transmission Line Proximity: A 345 kV line is also nearby but noted as "NOT AVAILABLE," reinforcing that the 115 kV system is the only viable Point of Interconnection (POI) at this location.

Recommended Interconnection Voltage: The only available POI is 115 kV (transmission). This is not recommended for a ≤5MW project. A project of this size would typically interconnect to a local distribution feeder (e.g., 13.2 kV or 13.8 kV). The absence of a nearby distribution substation is a potential fatal flaw for the project as currently conceived.

Estimated Cost & Timeline: A 115 kV interconnection would require a full transmission impact study through the regional grid operator, ISO New England (ISO-NE). Costs would be substantial, likely in the $3M - $7M+ range, including a high-voltage breaker, protection and control systems, a dedicated step-up transformer, and potential network upgrade costs. The ISO-NE queue timeline is notoriously long, often taking 3-5 years or more to reach a signed Interconnection Agreement.

Utility & Feeder Configuration: The local utility is likely Eversource. However, the interconnection process would be governed by ISO-NE, not Eversource's distribution-level process. There is no identifiable distribution feeder at this location; the infrastructure is purely for bulk power transmission.

4. Regulatory & Zoning Analysis

Authority Having Jurisdiction (AHJ): The City of Chicopee is the AHJ for all zoning and permitting.

Zoning Compatibility: The provided zoning is conflicting and highly problematic: "Vacant Land - Private Preserve, Open Space-Vacant Land" and "RESA" (likely Residential-A). None of these designations are compatible with an energy storage facility. "Preserve" and "Open Space" zoning is intended to prevent development, and residential zoning would not permit an industrial use like a BESS. This represents a major, potentially insurmountable, regulatory barrier.

Permitting Pathway: A BESS is not a by-right use in any of the listed zones. The project would require, at a minimum, a Use Variance and a Special Permit. A Use Variance is extremely difficult to obtain, as it requires proving a unique hardship with the land. A full rezoning of the parcel might even be necessary. This pathway is expensive, time-consuming (12-24 months), and has a very low probability of success, especially if there is public opposition from nearby residential areas.

Setback Requirements: Requires Verification: The specific BESS or utility-use setback requirements must be researched in the City of Chicopee Zoning Ordinance. However, given the likely proximity to residential zones, expect substantial setbacks from property lines (50-200 feet) and stringent noise limitations.

Moratorium Risk: The risk of a municipal moratorium on BESS projects is moderate to high, especially if this is one of the first such projects proposed in Chicopee. Public hearings associated with a variance or rezoning request could easily trigger a community-driven push for a moratorium.

5. IRA/ITC Incentive Analysis

Opportunity Zone: No. The site is not located in a qualified Opportunity Zone. (0% ITC Adder)

Energy Community: No. The site does not qualify under the statistical area or coal closure criteria. (0% ITC Adder)

Low-Income Community: No. The site does not appear to qualify for the Low-Income Communities Bonus Credit Program. (0% ITC Adder)

Potential Cumulative ITC Adder: 0%. This site is currently ineligible for any of the key location-based ITC adders. The project would only be eligible for the 30% base ITC (assuming it meets prevailing wage and apprenticeship requirements). The lack of any "stackable" credits makes the project's financial pro-forma significantly less attractive

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.