⚡ W WATER ST

Plymouth County, MA — Intake Report
📍 42.1226016, -70.9234658 📐 4.2 acres 🏷️ APN: 251 50_20_0 🔌 📅 Generated July 06, 2026 07:58 AM 🆔 MA003018
BESS Score: /10 Buildable: ac Nearest Sub: UNKNOWN161817 (0.6 mi) Zoning: Vacant Land - Residential-Vacant Land
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

DAVINE JULIE A TRUSTEE
4.2
251 50_20_0
Vacant Land - Residential-Vacant Land (RESIDE)
Plymouth County
25023
-

⚡ Infrastructure

UNKNOWN161817
0.6 mi
115 kV
115kV at 0.5 mi (TOWN OF MIDDLEBOROUGH - (MA))
102 ft
Not prime farmland
🔴 864 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Rockland

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

Road Access Quality: The property is located on W Water Street in Rockland, MA. A preliminary desktop review using satellite imagery indicates that W Water Street is a two-lane, paved local road. It appears to be in reasonable condition, but its width may be constrained, typical of residential areas. The street connects to major local arteries like Route 139 (Market Street), which should provide adequate access from regional highways for standard construction vehicles.

Equipment Delivery Feasibility: The primary concern for equipment delivery is navigating residential streets. While standard trucks should have no issue, the delivery of oversized and overweight components, such as the main power transformer (MPT) and multi-ton battery containers, presents a significant challenge. A detailed route survey would be required to assess turning radii at intersections, bridge weight limits, and the presence of low-hanging overhead utility lines. Access directly onto the 4.2-acre parcel from W Water Street appears feasible, but an improved construction entrance with a proper apron would need to be built.

Terrain Characteristics: Based on regional topography, the site is presumed to be relatively flat to gently rolling, which is advantageous for minimizing civil work and grading costs. However, this is an assumption. A formal ALTA/topographical survey is a critical next step to confirm site grades, identify any localized steep slopes, and plan for stormwater management.

Easement Concerns: As a vacant parcel, it is crucial to conduct a title search to identify any existing utility, access, or conservation easements that may encumber the property and restrict the buildable area. Furthermore, a new Right-of-Way (ROW) easement will be required to construct the 0.6-mile generation tie-line to the substation. Acquiring this ROW could be complex and costly, especially if it needs to cross third-party private properties or public roads.

2. Environmental Constraints

FEMA Flood Zone: The FEMA flood zone designation is currently unknown. This represents a critical data gap and a potential fatal flaw. Immediate action required: Review the effective FEMA Flood Insurance Rate Map (FIRM) for this parcel. If the site is located within a Special Flood Hazard Area (e.g., Zone A, AE), development costs will increase substantially due to requirements for elevating equipment above the Base Flood Elevation (BFE), and the project may be uninsurable or un-financeable.

Wetlands Presence: The presence of wetlands is unknown but highly probable in this region of Massachusetts. A desktop screening using MassGIS OLIVER is the first step, followed by a formal field wetland delineation by a certified professional. The Massachusetts Wetlands Protection Act imposes stringent regulations, including a 100-foot buffer zone ("Buffer Zone to Bordering Vegetated Wetland") where activities are restricted. The presence of significant wetlands could severely reduce the 4.2-acre buildable envelope, potentially rendering the site unusable for a 5MW BESS footprint.

Critical Habitat / Endangered Species: The initial data indicates no critical habitat or protected areas on site, which is a positive finding. However, this must be verified by cross-referencing the site location with the Massachusetts Natural Heritage & Endangered Species Program (NHESP) database to ensure no state-listed rare species or priority habitats are present, which could trigger additional review and mitigation requirements.

Brownfield/Superfund Status: The absence of nearby brownfield or superfund sites is a net positive, as it eliminates the risk of soil contamination and associated remediation liabilities. However, this also means the project is ineligible for the 10% IRA Brownfield Adder, a notable financial disadvantage compared to alternative sites.

Pipeline Proximity: The lack of major gas pipelines within a three-mile radius is a significant safety and layout advantage, removing concerns related to explosion risk, setback requirements, and coordination with pipeline operators.

3. Grid Infrastructure & Interconnection

Nearest Substation & Transmission: The site's proximity to grid infrastructure is its strongest attribute. The "UNKNOWN161817" substation is only 0.6 miles away, and a 115kV transmission line is 0.5 miles away. This short distance is highly desirable for minimizing the cost and complexity of the generation tie-line. The 115kV voltage class indicates a robust transmission-level point of interconnection (POI) with a high likelihood of available capacity for a 5MW project.

Recommended Interconnection: A transmission-level interconnection at 115kV is the recommended pathway. This avoids potential capacity constraints and power quality issues often found on distribution feeders and provides better access to wholesale energy markets. The interconnecting utility is Requires Verification but is likely National Grid or Eversource. The interconnection process will be governed by ISO New England (ISO-NE).

Estimated Cost & Timeline: Interconnection will be a major project cost. A preliminary, high

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.