⚡ 705 WAREHAM ST

Plymouth County, MA — Intake Report
📍 41.8078463, -70.7849003 📐 21.25 acres 🏷️ APN: 182 110-3996 🔌 📅 Generated July 06, 2026 02:49 PM 🆔 MA002808
BESS Score: /10 Buildable: ac Nearest Sub: SEMASS TAP (0.2 mi) Zoning: Commercial (Retail) - Commercial Building, Mail Order, Show Room
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

CD, LLP
21.25
182 110-3996
Commercial (Retail) - Commercial Building, Mail Order, Show Room (-)
Plymouth County
25023
-

⚡ Infrastructure

SEMASS TAP
0.2 mi
115 kV
115kV at 0.1 mi (NOT AVAILABLE)
83 ft
Farmland of statewide importance
🔴 53 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Middleborough

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

The subject property at 705 Wareham Street benefits from excellent road access, with direct frontage on Wareham Street (MA Route 28), a major state-level arterial road. Based on aerial and street-level imagery, Route 28 is a two-lane, paved road in good condition, capable of supporting heavy truck traffic. This is a significant advantage for the delivery of oversized and overweight equipment, including main power transformers, switchgear, and prefabricated battery energy storage containers. The direct frontage eliminates the need for complex, off-site access easements, reducing both cost and legal complexity.

The topography in this region of Plymouth County is generally flat to gently rolling, and satellite imagery of the parcel confirms this characteristic. There are no apparent steep grades or significant topographical challenges that would complicate civil engineering or site grading. Heavy equipment, such as large cranes required for setting transformers and enclosures, should be able to navigate the site with standard site preparation. A key unknown is the soil's load-bearing capacity, which must be confirmed with a geotechnical study. The current land use as a commercial building suggests that at least a portion of the site is already cleared and graded, potentially reducing initial civil work costs. However, demolition of the existing structure may be required, adding cost and complexity.

2. Environmental Constraints

The environmental profile of this site presents both significant unknowns and clear advantages. The most critical data gaps are the FEMA flood zone designation and the presence of wetlands, both of which are flagged as Requires Verification.

  • Flood Zone: An immediate desktop FEMA map review is required. If the site falls within a Special Flood Hazard Area (e.g., Zone AE), development costs will increase substantially due to requirements for elevating all critical equipment above the Base Flood Elevation, potentially making the project economically unviable.
  • Wetlands: Massachusetts has stringent wetland protection laws under the Wetlands Protection Act. The presence of regulated wetlands on the parcel could drastically reduce the buildable area due to required 100-foot buffer zones. A formal wetland delineation by a certified professional is a critical and immediate due diligence step.
  • Habitat & Protected Species: The data indicates no critical habitat or protected areas on or near the site, which is a significant de-risking factor, simplifying state and federal environmental permitting. This should be confirmed during a Phase I Environmental Site Assessment (ESA).
  • Contamination Risk: The absence of any nearby brownfield or superfund sites is a double-edged sword. It significantly lowers the risk of discovering soil or groundwater contamination, which would trigger costly remediation. However, it also means the project is ineligible for the 10% IRA brownfield tax credit adder, a notable financial disadvantage.
  • Pipeline Safety: The lack of any gas transmission pipelines within a three-mile radius is a major safety and permitting advantage, eliminating concerns related to blast zones and pipeline operator coordination.

3. Grid Infrastructure & Interconnection

The site's proximity to robust grid infrastructure is its single greatest asset. The SEMASS TAP substation is located only 0.2 miles from the parcel. This extremely short distance for a gen-tie line will dramatically reduce interconnection costs compared to sites further from a viable Point of Interconnection (POI). The substation's maximum voltage of 115 kV indicates it is a transmission-level substation, suitable for a utility-scale BESS project.

The likely interconnection pathway would be a new 115 kV transmission line from the project site directly to a new bay at the SEMASS TAP substation. While a 115 kV line is noted as being 0.1 miles away, its status as "NOT AVAILABLE" suggests a direct line tap is not feasible, reinforcing the substation as the primary POI. Given the 115 kV infrastructure, this project is firmly in the utility-scale category, likely targeting participation in ISO-New England wholesale markets. An interconnection application would need to be submitted to ISO-NE, a process known for being lengthy and complex, often taking 3-5 years to move through the queue to a signed Interconnection Agreement.

The interconnecting utility is Requires Verification but is almost certainly National Grid based on service territory maps. Initial interconnection cost estimates for a 0.2-mile, 115 kV gen-tie and substation upgrades could range from $2.0M to $4.0M, though this is highly dependent on the results of the ISO-NE system impact studies.

4. Regulatory & Zoning Analysis

The Authority Having Jurisdiction (AHJ) is the Town of Middleborough. The provided zoning is listed as "Commercial (Retail)" and "GUX" (General Use). Neither of these designations likely permits a utility-scale BESS project "by-right." Battery storage is a relatively new use, and many municipal bylaws do not explicitly address it.

Therefore, the most probable permitting pathway will be a Special Permit from the Middleborough Planning Board. This process involves a public hearing, site plan review, and discretionary approval from the board. It introduces significant timeline risk and uncertainty. Key to this process will be demonstrating that the project will not create adverse impacts related to noise, visual aesthetics, and safety. We must immediately research the Middleborough Zoning Bylaws to determine if they have specific provisions or performance standards for BESS or general utility uses. Setback requirements from property lines, residential zones, and any identified wetlands will be critical design constraints. A significant risk is the potential for a local moratorium on BESS development, which has occurred in other Massachusetts towns. Early, informal outreach to the Town Planner is highly recommended to gauge the town's receptiveness to such a project.

5. IRA/ITC Incentive Analysis

The project's eligibility for Investment Tax Credit (ITC) adders under the Inflation Reduction Act (IRA) is poor, which presents a major financial challenge.

  • Opportunity Zone: No. (0% adder)
  • Energy Community: No. (0% adder)
  • Low-Income Community: No. (0% adder)

As a result, the project will only be eligible for the base 30% ITC (contingent on meeting prevailing wage and apprenticeship labor requirements). It will not

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.