⚡ 91 FREDETTE ST

Worcester County, MA — Intake Report
📍 42.5709959, -72.0120771 📐 2.12 acres 🏷️ APN: 103 M22-11-7 🔌 📅 Generated June 30, 2026 02:15 AM 🆔 MA002385
BESS Score: /10 Buildable: ac Nearest Sub: UNKNOWN133570 (1.1 mi) Zoning: Heavy Industrial And Transportation/Communication - Truck Terminal (Motor Freight)
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

MANCA JOHN F & DORINA G TRSTES
2.12
103 M22-11-7
Heavy Industrial And Transportation/Communication - Truck Terminal (Motor Freight) (-)
Worcester County
25027
-

⚡ Infrastructure

UNKNOWN133570
1.1 mi
69 kV
None within ~3 miles
960 ft
Not prime farmland
🔴 606 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
13 site(s) within ~2 mi

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Gardner

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

Initial desktop analysis indicates the property at 91 Fredette Street has excellent site access for a BESS project. The parcel has direct frontage on Fredette Street, a paved industrial road that connects to major local thoroughfares like Pearl Street and Route 2. Based on satellite imagery, the site is currently used as a truck terminal and trailer parking lot, suggesting it is graded, compacted, and capable of supporting heavy vehicle traffic.

The topography appears to be predominantly flat and cleared, which is ideal for minimizing civil engineering and construction costs. The existing use significantly de-risks the delivery and staging of heavy equipment. Large trucks carrying battery containers, inverters, and the main power transformer should have no issue accessing the site directly from the public right-of-way. The primary concern regarding access would be the acquisition of a temporary construction easement for laydown and staging, which may require negotiation if adjacent parcels are needed. No immediate access easement concerns for reaching the property itself are apparent, as it has direct road frontage. A formal ALTA survey is required to confirm topography and identify any unrecorded easements.

2. Environmental Constraints

The environmental profile of this site presents both significant risks and a potential opportunity.

  • FEMA Flood Zone & Wetlands: Requires Verification. The FEMA flood zone status and presence of jurisdictional wetlands are currently unknown. This is a critical data gap. A desktop screening using MassGIS and federal databases must be conducted immediately. Given the industrial development in the area, the risk of extensive wetlands may be low, but any presence could severely constrain the buildable area on this small 2.12-acre parcel and require significant setbacks.
  • Brownfield/Superfund Status: The presence of 13 known brownfield or superfund sites within a two-mile radius is a major red flag for potential site contamination. The historical and current use as a truck terminal is a "Recognized Environmental Condition" (REC) that necessitates a Phase I Environmental Site Assessment (ESA). While this presents a risk of costly remediation, it also creates a significant opportunity. If the site can be officially classified as a brownfield under IRA guidelines, the project would be eligible for a 10% ITC adder, which could be critical to project economics.
  • Critical Habitat & Protected Areas: The data indicates no critical habitats or protected areas on or immediately adjacent to the site. This is a significant advantage, as it should streamline the environmental permitting process and avoid potential conflicts with state or federal wildlife agencies.
  • Pipeline Proximity: The absence of major gas transmission pipelines within a three-mile radius is a positive safety factor, eliminating the need for specialized pipeline impact studies and associated setback requirements.

3. Grid Infrastructure & Interconnection

The grid infrastructure presents the most significant challenge for this site. The nearest substation (UNKNOWN133570) is located approximately 1.1 miles away. This is a considerable distance for a distribution-scale project and will likely result in a high interconnection cost.

  • Interconnection Point: The substation has a 69 kV bus, which is transmission voltage. However, it will almost certainly have a distribution-level bus (likely 13.8 kV) from which the project would interconnect. The project's scale (likely <5 MW) makes a distribution-level connection the only financially viable option.
  • Interconnecting Utility: The utility for Gardner, MA is National Grid. Their interconnection process in Massachusetts is well-defined but can be lengthy, often taking 12-24 months from application to commercial operation.
  • Feeder Configuration: A 1.1-mile line run will almost certainly require a new, dedicated feeder to be constructed from the substation to the project site. The cost for this work, including trenching/boring, conduit, cable, and any necessary road or utility crossings, could be substantial.
  • Estimated Cost & Timeline: A preliminary, high-level estimate for a 1.1-mile distribution line extension is in the range of $1.5M - $2.5M. This is a major project cost that could render the site uneconomical. A formal interconnection pre-application must be filed with National Grid as a top priority to obtain a more accurate cost estimate. The study process alone could take 6-9 months.

4. Regulatory & Zoning Analysis

The regulatory outlook for this site is highly favorable. The Authority Having Jurisdiction (AHJ) is the City of Gardner.

  • Zoning Compatibility: The parcel is zoned IND2 (Heavy Industrial), which is an ideal designation for a BESS facility. Energy storage is typically considered a light industrial or utility use, making it highly compatible with the existing zoning code.
  • Permitting Pathway: While a detailed review of the Gardner Zoning Ordinance is required, the likely permitting pathway would be a Special Permit from the Gardner Planning Board. It is unlikely to be a by-right use but should not require a more arduous variance. This process involves a public hearing but is a standard and predictable path for development in an industrial zone.
  • Setbacks & Restrictions: Standard industrial zone setbacks for front, side, and rear yards will apply. More importantly, the design must adhere to NFPA 855 standards for BESS installation, which dictate separation distances between battery containers and from property lines and public ways. On a 2.12-acre lot, these fire safety setbacks will be a primary driver of the final site layout and achievable project size. There are no known moratoriums on BESS development in Gardner, but this must be confirmed with the Planning Department.

5. IRA/ITC Incentive Analysis

The site's eligibility for IRA/ITC adders is limited, which

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.