⚡ 40 MILLBURY RD

Worcester County, MA — Intake Report
📍 42.1467663, -71.853093 📐 12.58 acres 🏷️ APN: 226 16_D03 🔌 📅 Generated July 05, 2026 03:50 AM 🆔 MA001367
BESS Score: /10 Buildable: ac Nearest Sub: NORTH OXFORD (1.5 mi) Zoning: Vacant Land - Private Preserve, Open Space-Vacant Land (Forest L
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

EAMES, D EDWIN
12.58
226 16_D03
Vacant Land - Private Preserve, Open Space-Vacant Land (Forest L (R1)
Worcester County
25027
-

⚡ Infrastructure

NORTH OXFORD
1.5 mi
115 kV
345kV at 0.9 mi (FITCHBURG GAS AND ELECTRIC LIGHT COMPANY)
632 ft
Not prime farmland
🔴 99 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Oxford

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

1. Site Access & Topography

Road Access & Equipment Delivery: The property is located at 40 Millbury Road. Initial mapping analysis indicates this is a "flag lot," with access provided via a long, narrow driveway or private road extending from Millbury Road itself. Millbury Road appears to be a two-lane, paved local road. While suitable for standard vehicles, its suitability for heavy-haul trucks carrying multi-ton transformers and 40-foot battery containers is a significant concern. A detailed logistics review is required to assess turning radii from the main road, the width and grade of the access drive, and any potential weight-limited culverts or bridges. Requires Verification: A physical site visit and consultation with a logistics contractor are essential to confirm heavy equipment access feasibility.

Terrain & Buildability: The current land use is designated as "Forest Land." This strongly suggests the 12.58-acre parcel is heavily wooded and has undeveloped, potentially varied topography. Site development will require substantial tree clearing, stumping, and grading to create a level pad for the BESS compound, switchgear, and transformer. A geotechnical investigation will be mandatory to determine soil stability, bearing capacity, and the extent of rock ledge, which could significantly increase foundation costs. The long access drive will also need to be cleared and constructed to an industrial standard.

Easement Concerns: As a flag lot, the legal status of the access drive is a critical diligence item. We must verify that a legally recorded, permanent, and sufficiently wide access and utility easement exists for the benefit of this parcel. The easement must explicitly permit utility-scale construction traffic and the installation of underground or overhead electrical conduits. Any ambiguity in the easement language could be a fatal flaw for the project.

2. Environmental Constraints

FEMA Flood Zone & Wetlands: The FEMA flood zone status is currently unknown. This is a critical data gap. A review of FEMA's Flood Insurance Rate Maps (FIRMs) is an immediate next step. If the buildable area is within a Special Flood Hazard Area (e.g., Zone AE), it would necessitate raising all equipment above the Base Flood Elevation, adding substantial cost and complexity. Given the forested nature of the site in Massachusetts, the presence of state or federally regulated wetlands is highly probable. A wetland delineation by a certified professional will be required. Under the Massachusetts Wetlands Protection Act, activities are restricted within 100 feet of wetlands (Buffer Zone), which could severely constrain the usable acreage of the parcel.

Habitat, Brownfields, & Pipelines: The site shows no known critical habitat, protected species, or proximity to designated protected areas, which is a positive initial finding. However, this must be formally verified through a query of the MA Natural Heritage & Endangered Species Program (NHESP) database. The absence of nearby brownfield or superfund sites means the project is not eligible for the 10% IRA Brownfield Adder, but it also avoids potential environmental liability and cleanup costs. The lack of pipelines within a 3-mile radius is a significant safety and layout advantage, eliminating concerns about explosion risk and associated setbacks.

3. Grid Infrastructure & Interconnection

Substation & Transmission Proximity: The nearest substation is National Grid's North Oxford Substation, located approximately 1.5 miles away. This is a considerable distance for a distribution-scale project. The substation's 115 kV bus is a sub-transmission voltage, but it will certainly have distribution-level voltage feeders (e.g., 13.8 kV) exiting the facility, which would be the target for our interconnection. A 345 kV transmission line is closer (0.9 miles), but tapping a line of this voltage is financially and technically infeasible for a project of this scale (≤5MW).

Interconnection Strategy & Cost: The only viable path is a distribution-level interconnection to a local feeder, likely at 13.8 kV. The primary challenge is the 1.5-mile distance to the substation. We must determine if a suitable 3-phase feeder already runs along Millbury Road adjacent to the property. If not, the project would bear the full cost of a 1.5-mile line extension, including poles, conductors, and any necessary road crossing or ROW acquisition. This could easily place interconnection costs in the $1.5M - $3.0M+ range, potentially rendering a ≤5MW project uneconomical. The interconnecting utility is almost certainly National Grid, and the project would enter the ISO-New England (ISO-NE) interconnection queue. Timelines from application to Commercial Operation in this queue can be lengthy, often spanning 2-4 years.

4. Regulatory & Zoning Analysis

Jurisdiction and Zoning: The Authority Having Jurisdiction (AHJ) is the Town of Oxford, MA. The parcel's zoning is listed as R-1 (Residential) and described as "Private Preserve, Open Space-Vacant Land." This zoning is a major impediment. Battery energy storage is an industrial/utility use and is fundamentally incompatible with a residential or open space designation. It is highly unlikely that BESS is a permitted use "by-right" in this zone.

Permitting Pathway and Risk: A review of the Town of Oxford's zoning bylaws is required to see if BESS is defined. If not, it will be treated as an unlisted use. The permitting pathway will not be simple; it will require a discretionary approval from the Zoning Board of Appeals (ZBA), likely in the form of a Use Variance or a Special Permit

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.