⚡ 14 HOWARD ST

Worcester County, MA — Intake Report
📍 42.2937025, -71.8803998 📐 2.79 acres 🏷️ APN: 228 29_32 🔌 📅 Generated June 25, 2026 01:35 PM 🆔 MA001000
BESS Score: /10 Buildable: ac Nearest Sub: COOKS POND (1.6 mi) Zoning: Vacant Land - Residential-Vacant Land
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

LANDERS BRIAN J TRUSTEE
2.79
228 29_32
Vacant Land - Residential-Vacant Land (R40)
Worcester County
25027
-

⚡ Infrastructure

COOKS POND
1.6 mi
69 kV
115kV at 2.6 mi (FITCHBURG GAS AND ELECTRIC LIGHT COMPANY)
1103 ft
Not prime farmland
🔴 143 structures within 0.5 mi (setback/opposition risk)

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
None within ~2 miles

💰 IRA/ITC Adders

No
No
No

🏛️ Jurisdiction

Loading from layers...

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

Site Access & Topography

The subject property at 14 Howard Street is a 2.79-acre parcel located in a residential area of Paxton, MA. Access is directly from Howard Street, which appears to be a local, secondary road. Immediate verification is required to determine if Howard Street is paved and wide enough to accommodate heavy construction traffic, including low-boy trailers for transformer delivery and flatbeds for battery containers (typically 40-53 feet long). The turning radius from any main thoroughfares onto Howard Street must also be assessed. Given the residential context, there is a high risk of road limitations and potential for community opposition to heavy vehicle traffic.

The topography in Worcester County is typically characterized by rolling hills, wooded areas, and rocky soil. While a formal survey is needed, we should assume the site is not perfectly flat. A grading plan will likely be required, increasing civil engineering costs. The small parcel size (2.79 acres) means that any significant slopes could severely constrain the buildable area for a 5MW BESS, which requires approximately 1.5-2 acres of flat, usable land. The ability for heavy equipment like a 100-ton crane (for transformer setting) to access and operate safely on site is a significant concern that hinges on both road access quality and on-site geotechnical conditions. No access easements appear necessary for frontage on Howard Street, but temporary construction or utility easements across neighboring properties might be required for the interconnection route, which adds complexity and cost.

Environmental Constraints

The environmental profile of this site presents several critical unknowns that must be resolved immediately.

  • FEMA Flood Zone: The "Unknown" status is a high-priority risk. A review of FEMA's Flood Insurance Rate Maps (FIRMs) is the first step. If the site falls within a Special Flood Hazard Area (e.g., Zone A or AE), development costs will increase substantially due to the need for elevated foundations for all equipment. In some cases, it can render a site undevelopable.
  • Wetlands: The "Unknown" status for wetlands is another potential fatal flaw. Central Massachusetts is rich with wetlands, and the Massachusetts Wetlands Protection Act imposes stringent regulations, including a 100-foot buffer zone around Bordering Vegetated Wetlands (BVW). On a small 2.79-acre parcel, the presence of regulated wetlands could eliminate the required buildable area. A desktop screening using MassGIS data is an immediate next step, likely to be followed by a formal field delineation by a wetland scientist.
  • Habitat & Protected Species: The initial screening shows no critical habitat, which is a positive indicator. However, this must be verified against the Massachusetts Natural Heritage & Endangered Species Program (NHESP) database to ensure no state-listed species or priority habitats are present.
  • Brownfield/Superfund: The absence of nearby brownfield or superfund sites is positive from a liability and cleanup perspective. However, it also means the site is ineligible for the 10% IRA Brownfield Adder, which is a significant disadvantage for project economics.
  • Pipeline Proximity: The lack of major gas pipelines within three miles is a notable safety and design advantage, eliminating the need for specialized setbacks or risk assessments related to pipeline incidents.

Grid Infrastructure & Interconnection

The grid infrastructure presents the most significant challenge for this site. The nearest substation, Cooks Pond, is 1.6 miles away. For a distribution-scale project (≤5MW), this is a substantial and likely cost-prohibitive distance for a new feeder line extension. The substation's 69kV bus is a sub-transmission voltage; while a 69kV interconnection is possible, it is far more complex and expensive than a standard distribution connection (e.g., 13.2kV or 13.8kV). The nearest transmission line (115kV at 2.6 miles) is not a viable Point of Interconnection (POI) for a project of this scale due to exorbitant costs.

The recommended interconnection path would be to a local 3-phase distribution feeder. The primary unknown is the location, voltage, and available capacity of the nearest 3-phase circuit. The interconnecting utility is almost certainly National Grid. We must immediately submit an interconnection pre-application to National Grid to identify the most viable POI. Assuming a new distribution line must be built for 1.6 miles, the estimated interconnection cost would likely be in the $2.0M - $4.0M range, including utility upgrades, line construction, and protection equipment. The ISO-New England (ISO-NE) interconnection queue is notoriously congested and slow; a realistic timeline from application to commercial operation could easily exceed 36 months. This combination of high cost and long timeline severely undermines the project's viability.

Regulatory & Zoning Analysis

The regulatory landscape is unfavorable. The Authority Having Jurisdiction (AHJ) is the Town of Paxton. The parcel's zoning is listed as R40 (Residential, 40,000 sq. ft. minimum lot) and GRB (General Residence B). Battery Energy Storage is not a permitted use "by-right" in any residential zone in Massachusetts.

Therefore, the permitting pathway would be highly discretionary and high-risk. It would require, at a minimum, a Special Permit from the Planning Board and/or a Use Variance from the Zoning Board of Appeals (ZBA). A Use Variance has a very high legal bar to clear, requiring the applicant to prove a unique hardship related to the land itself. This process invites significant public scrutiny and opposition, particularly from abutting residential property owners. There is a high probability of denial. Furthermore, many Massachusetts towns, when faced with BESS applications in the absence of specific bylaws, have enacted temporary moratoriums to study the issue. Paxton could easily do the same, halting the project indefinitely. This zoning designation is a near-fatal flaw.

IRA/ITC Incentive Analysis

The project's eligibility for Investment Tax Credit (ITC) adders under the Inflation Reduction

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.