TO: Sunland America Corp. Development Committee
FROM: Senior BESS Site Evaluation Analyst
DATE: October 26, 2023
SUBJECT: Comprehensive Site Diligence Analysis for Project "Renaissance"
PROPERTY: 1480 RENAISSANCE DR, Park Ridge, Cook County, IL (APN: 09221100050000)
FINAL RECOMMENDATION: MAYBE
This report provides a comprehensive due diligence analysis for the subject property as a potential site for a distribution-scale (≤5MW) Battery Energy Storage System (BESS). The site presents a compelling financial case due to significant IRA incentives but faces substantial regulatory and grid interconnection hurdles. The project viability is contingent on successfully navigating a challenging permitting process and confirming grid capacity. Proceeding with the recommended next steps is advised to de-risk these key variables before committing significant capital.
The site exhibits excellent physical access, a significant advantage for construction and operations. Located within a well-developed commercial office park, the property is served by Renaissance Drive, a public, paved road with direct connections to major arterials like East Touhy Avenue and Interstate 294. This existing infrastructure is well-suited for the delivery of heavy equipment, including tractor-trailers carrying battery containers, switchgear, and pad-mount transformers.
Based on aerial imagery and regional geographic data, the topography is presumed to be flat, which is characteristic of the Chicagoland area. This will minimize the need for extensive civil work and grading, reducing site preparation costs. The 2.97-acre parcel size (per Regrid data, which conflicts with a 35.02-acre figure in other data sources; this must be verified) appears sufficient for a 5MW/20MWh BESS layout, including necessary access roads, equipment pads, and fire safety setbacks.
A key concern is the potential for restrictive easements. As part of a larger planned development, the parcel is likely subject to utility, access, or drainage easements that could encumber the buildable area. A full ALTA survey and title report are critical early-stage requirements to confirm the unencumbered buildable envelope.
The environmental profile of the site presents both opportunities and risks that require immediate investigation.
Grid access is a primary challenge for this site. While a 138kV Commonwealth Edison (ComEd) transmission line is located 1.5 miles away, a transmission-level interconnection for a ≤5MW project would be prohibitively expensive. Therefore, the only viable path is a distribution-level interconnection.