⚡ 1480 RENAISSANCE DR

Cook County, IL — Intake Report
📍 42.0336601, -87.8646427 📐 35.02 acres 🏷️ APN: 9221100050000 🔌 6fb54528-966c-4764-bda6-1e20dc045eb5 📅 Generated June 28, 2026 10:51 AM 🆔 IL001590
BESS Score: /10 Buildable: ac Nearest Sub: - (-) Zoning: Commercial (Office) - Office Bldg (Multi-Story)
🗺️ Map
📐 Site Layout
📋 Overview
🤖 AI Analysis
📝 Notes

🔍 Site Diligence

Complete these items. Changes save automatically.
AHJ Confirmed
Verify governing jurisdiction via municipality overlay
Zoning Verified
Confirm BESS-compatible zoning or CUP/SUP pathway
Flood/Wetlands Clear
FEMA Zone X or buildable area avoids flood/wetlands
Site Access Confirmed
Road access, easements, equipment delivery route
Substation Feasibility
Nearest substation capacity and voltage suitable
Setback Analysis
Buildable acreage accounts for required setbacks
Environmental Clear
No endangered species, conservation areas, brownfield issues
Title Clear
No liens, encumbrances, or easement conflicts

📝 Diligence Fields

🏠 Property Details

IMPERIAL REALTY CO -
35.02
9221100050000
Commercial (Office) - Office Bldg (Multi-Story) (-)
Battery Energy Storage
Cook County
17031

⚡ Infrastructure

6fb54528-966c-4764-bda6-1e20dc045eb5
-
-
- kV
138kV at 1.5 mi (COMMONWEALTH EDISON CO)
633 ft
Not prime farmland
🔴 941 structures within 0.5 mi (setback/opposition risk)
Public

🌊 Environmental

Loading...
Loading...
N/A (non-MD)
None within ~3 miles
None within ~2 miles
None
None
1 site(s) within ~2 mi

💰 IRA/ITC Adders

No
Yes — Fossil Fuel Employment (FFE Area)
No

🏛️ Jurisdiction

Park Ridge
City
Park Ridge

📊 Assessment

/10

🤖 AI Site Assessment — Gemini Deep Research

MEMORANDUM

TO: Sunland America Corp. Development Team

FROM: Senior BESS Site Evaluation Analyst

DATE: October 26, 2023

SUBJECT: Comprehensive Site Diligence Analysis for "Project Ridge"

Property: 1480 RENAISSANCE DR, Park Ridge, Cook County, IL (APN: 09221100050000)


This report provides a comprehensive preliminary due diligence analysis for the potential acquisition and development of a distribution-scale Battery Energy Storage System (BESS) at the subject property. The analysis identifies key site attributes, significant risks, and critical next steps required to advance the project. The site shows considerable promise due to its location and strong financial incentives, but it is encumbered by significant unknowns related to grid access and permitting that must be resolved before committing further capital.

1. Site Access & Topography

Road Access & Feasibility: The site benefits from excellent public road access via Renaissance Drive, located within a well-developed commercial office park. This road connects to major thoroughfares, providing a clear and straightforward route from regional highways like I-294. The existing infrastructure consists of wide, paved, commercial-grade roads capable of supporting heavy haul trucks required for delivering large equipment such as transformers, switchgear, and containerized BESS units.

Terrain & Equipment Access: The topography in Park Ridge, and Cook County generally, is exceptionally flat. This is a significant advantage, minimizing the need for extensive civil work and grading, thereby reducing site preparation costs. The flat terrain ensures that heavy equipment, including large cranes for setting transformers and BESS enclosures, can easily access and maneuver within the parcel boundaries.

Easement Concerns: While access to the parcel boundary is secure via public right-of-way, diligence is required to confirm internal site conditions. We must verify that no existing utility or access easements cross the proposed development footprint. Furthermore, a new utility easement will need to be negotiated with the property owner and Commonwealth Edison for the interconnection line from the Point of Interconnection (POI) to our project substation. The route for this gen-tie line is a critical unknown.

A notable data discrepancy exists regarding parcel size (35.02 acres vs. 2.97 acres). This must be clarified immediately, as our analysis assumes the 2.97-acre parcel is the target, which is appropriate for a ≤5MW project.

2. Environmental Constraints

FEMA Flood Zone: Requires Verification. The FEMA flood zone designation is currently unknown and represents a critical risk. A desktop review of FEMA Flood Insurance Rate Maps (FIRMs) is an immediate priority

📸 Satellite Inspection

Satellite Close-up
Close-up (Zoom 17)
Satellite Wide
Context View (Zoom 14)
Terrain Map
Terrain / Roads

📝 Add Note

📋 Note History

No notes yet. Add the first note above.